Pictured in this photo included in a Columbia Gas Transmission LLC letter to the Federal Energy Regulatory Commission dated Nov. 4, 2024 is what the company said was restoration progressing near a well pad that was used for storage, with work on fabrication and pipe installation in the background, for a company gas storage and pipeline project near Pinch in Kanawha County.
Facilities comprising an extensive gas storage and pipeline project in Kanawha County have been placed into service, developers told federal regulators Monday.
Columbia Gas Transmission LLC on Monday said in a filing with the Federal Energy Regulatory Commission that facilities were placed into service on Nov. 8 for its project, which has included new gas storage wells on a new well pad and construction of roughly 600 feet of related pipeline.
Pictured in this photo included in a Columbia Gas Transmission LLC letter to the Federal Energy Regulatory Commission dated Nov. 4, 2024 is what the company said was restoration progressing near a well pad that was used for storage, with work on fabrication and pipe installation in the background, for a company gas storage and pipeline project near Pinch in Kanawha County.
Last year, the Houston-based company told the commission it was moving forward with its plan to construct and operate two new injection and withdrawal wells, and 586 feet of related pipeline, as well as abandon more than 5,000 feet of pipeline in the Coco B storage field near Pinch.
Last month, the commission granted a Columbia request to place the facilities into service. The agency noted in its approval letter that Columbia had fully restored project well pad areas and that restoration of the remaining pipeline portion of the project was “proceeding satisfactorily.†FERC approval of the project came in February 2023.
In a Nov. 4 letter to the commission, Columbia included project photos that it said showed restoration progressing near a well pad while work on well lines and pipeline installation moved forward in the background.
In a letter last year, Columbia told the Federal Energy Regulatory Commission, which approved the project in February, that “bona fide construction activities†began Dec. 18, 2023.
The project was planned within 50 feet of 10 residences.
Plugging and abandoning 4,927 feet of pipeline in place
Abandoning 251 feet of pipeline by removal
Plugging and abandoning four injection and withdrawal wells
Columbia said it aimed to protect the storage field’s integrity by abandoning the four existing wells because of their integrity and use the new wells to maintain storage field deliverability. Abandoning the old wells would reduce physical location risk in line with a federal Pipeline Hazardous Materials Safety Administration rule on well storage, according to a FERC environmental assessment for the project.
Ten residences, five nonresidential structures and one inactive commercial structure were within 50 feet of proposed project construction areas. Columbia prepared a residential construction plan for each of the three residences within 25 feet of those areas.
The residences are near the Upper Pinch Estates road north of Upper Pinch Road above Pinch Creek, just west of the First Baptist Church of Pinch.
Estimated construction emissions were projected at roughly 43 tons of carbon dioxide equivalent and 171 tons of particulate matter in 2023, according to the assessment.
The project was slated to cross eight bodies of water, including Pinch Creek, and unnamed tributaries to the creek and Potato Fork.
FERC staff predicted that significant flooding effects aren’t expected, because of the relatively small area within the Special Flood Hazard Area to be permanently affected.
TC Energy acquired the Columbia Gas Transmission system in 2016.